La Línea 1 del Metro de Bogotá alcanza casi 40% de avance en dos años y consolida hitos claves en 2025

Periodista Portafolio22.12.2025 12:55 Actualizado: 22.12.2025 16:44

La Línea 1 del Metro de Bogotá alcanza casi 40% de avance en dos años y consolida hitos claves en 2025

TL;DR

  • Metro Line 1's execution advanced by approximately 40% in two years, reaching 68.64% by November 2025.
  • The Calle 72 interchange, a crucial integration point, became operational in early 2025.
  • The first trains and multipurpose vehicles for Line 1 arrived in Bogotá after a long journey from China.
  • Over nine kilometers of elevated viaduct were assembled using eight launching gantries.
  • Construction progressed on the Bosa workshop yard, including administrative buildings, maintenance workshops, and a 25,000 sq meter depot for 30 trains.
  • Rail installation began in the workshop yard and on the viaduct, enabling the start of dynamic testing.
  • Line 1 trains will operate with GoA4 automation, enabling fully automatic, driverless circulation.
  • The Metro de Bogotá joined the Latin American Association of Metros and Subways (Alamys) and the International Association of Public Transport (UITP).
  • Citizen culture initiatives engaged over 46,200 people through the School Car and various workshops.
  • A pilot plan to prevent street sexual harassment at construction sites was launched.
  • Scheduled for 2026 are the delivery of the second bridge at Pulpo sector and the start of train testing on a 5.7 km section.