El Metro de Bogotá ya hizo su primera prueba autónoma de rodaje: ¿cómo le fue y qué sigue?

Avanza el proyecto del Metro de Bogotá Foto: PORTAFOLIO

El Metro de Bogotá ya hizo su primera prueba autónoma de rodaje: ¿cómo le fue y qué sigue?

TL;DR

  • Dynamic testing of the first Bogotá Metro trains commenced on December 26, 2025.
  • Three trains are currently in Bogotá, with a fourth arriving on January 8, 2026, and subsequent arrivals every 15 days, totaling 30 trains by October 2026.
  • Initial tests involve a driver operating the train on a 1-kilometer test track within the workshop yard, reaching speeds up to 80 km/h.
  • The project aims to complete 70% of its construction by the end of 2025.
  • By the first half of 2026, trains are expected to operate on over 5,000 meters of the viaduct.
  • The first four stations are planned to be completed in shell form by May or June 2026.
  • Enel Colombia invested approximately $60 billion to energize the El Porvenir substation, powering the workshop yard.
  • Commercial operation is targeted for March 2028.
  • Total investment to date is $6.1 trillion, with an additional $5.3 trillion needed for 2026.
  • The project is financed by Bogotá (70%) and the Nation (30%) through future vigencies, supplemented by multilateral bank loans.
  • A funding gap of $1.8 trillion is anticipated for 2027, requiring an additional credit.