Al 90% va el avance de Ecopetrol con las comunidades para continuar con el desarrollo del Parque Eólico Windpeshi
Bayron Triana, vicepresidente de Energías para la Transición de Ecopetrol revela avances del proyecto Winspeshi. Foto: Cortesía: Ecopetrol

TL;DR
- Communities in La Guajira support the Windpeshi Wind Farm and transmission line construction.
- Support follows three months of intercultural dialogue characterized by respect and transparency.
- Ecopetrol aims to make La Guajira an energy transition development hub.
- Over 90% of prior consultation agreements for the two projects have been received.
- The Windpeshi project will feature 41 wind turbines with a total capacity of 205 MW.
- The farm is expected to generate approximately 8% of Ecopetrol Group's energy consumption.
- It will prevent over 140,000 tons of CO₂ emissions annually.
- Infrastructure includes a 180 MVA substation and a 60-kilometer transmission line.